These are our prices for a double-skin (230 mm) stock-brick wall with brickforce and pillars about every 3 m. Each range runs from a new wall on open ground (the lower price) to replacing an old wall (the higher price, because the old wall has to be demolished and the rubble carted away).
| Wall size | Stock brick, not plastered | Plastered both sides |
|---|---|---|
| 10 m × 1.8 m | R26 000 – R28 700 | R31 000 – R33 700 |
| 10 m × 2.1 m | R28 400 – R31 100 | R34 200 – R36 900 |
| 20 m × 1.8 m | R49 900 – R53 400 | R59 900 – R63 400 |
| 20 m × 2.1 m | R54 700 – R60 100 | R66 400 – R71 800 |
| 30 m × 1.8 m | R73 900 – R80 100 | R88 900 – R95 100 |
| 30 m × 2.1 m | R81 100 – R89 200 | R98 600 – R106 800 |
Estimates from our online calculator, October 2026, with VAT included in our material costs. Your fixed price is confirmed in writing after a free site visit.

Face brick prices
A face brick wall needs no plaster or paint, and the price depends on the brick you choose. We price three ranges of brick, and you pick the exact brick and colour at the site visit. These are the prices for a 20 m × 1.8 m wall with face brick on both sides, from a new wall on open ground to replacing an old wall.
| Face brick | Bricks | 20 m × 1.8 m wall |
|---|---|---|
| Budget | Satin and dapple bricks | R66 000 – R69 500 |
| Standard | More colours and textures | R73 500 – R77 000 |
| Premium | Corobrik Travertine | R97 600 – R101 000 |
What is included
- Concrete foundation, dug and poured
- Brick wall with brickforce, and pillars
- All materials: bricks, cement, sand, stone, and delivery
- For an old wall: demolition and rubble removal before the new wall goes up
- For plastered walls: plaster on both sides, pillars and tops
Painting, gates, electric fencing and palisade tops are not part of our service.
Every wall is checked against our written quality standard and has a 6-month workmanship guarantee.
What changes the price
- Length. Most of the cost is per metre, so double the wall is roughly double the price. Delivery is a fixed charge for each job.
- Height. A taller wall needs more bricks and more labour. Walls above 2 m cost more per metre to build.
- Plaster. Plastering both sides adds roughly R500 to R585 per metre, depending on height. See the plaster price guide.
- Old wall or open ground. Replacing an old wall adds demolition and rubble removal, about R290 per metre at 1.8 m. A wall on ground that never had a foundation needs steel in the foundation, about R115 per metre, but has nothing to demolish, so open ground costs less.
- Site conditions. Slopes, difficult access and poor ground conditions (such as rock or soft soil) can change the work, which is why we confirm the price on site.
- Distance. Our prices are the same across the areas we serve. Jobs outside Johannesburg may include a travel charge.
Do I need approval?
In Johannesburg, a boundary wall higher than 1.8 m needs the City's written consent under the Land Use Scheme. Retaining walls and structural walls usually need approved plans as well. Read our guide to boundary wall approval in Johannesburg.
How long does it take?
A crew of six builds an average 20 m wall in about 6 days, plastering included. Longer or higher walls take more time, and we confirm the timing in your written quote.